Update on Cluj Regional Emergency Hospital

Update on Cluj Regional Emergency Hospital

Full speed ahead for the new Cluj Regional Emergency Hospital! 🚀Work is progressing fast on WP1 (work package 1 – enabling works). 🚧

By mid-August, dehydration and drainage of the site were completed, while excavation and construction of the retaining wall are ongoing. In parallel, the tender for WP2, for the construction of the hospital building itself, has been launched. ️📝 On this occasion we share new renderings of the project.